Work completed in the last two weeks
- Highway work completed
- Completed more work on Upper Podunk, ditching hay and seed
- Turn-around installed at the end of Sheldon Hill rd
- Touch up grading in areas that are rough
- GMP contractors still working on top coating a road with a hope to be finished by the end of the month
- Maintenance
- Loader needed new control solenoid, should be back up and running in less than a week.
- Plow frames installed on all the trucks
- Spinners pulled out, cleaned up and checked
- T1 and T3 winter tires are on
- Tire chains have been delivered
- Plow edges checked, ready to go
- Truck body chains tested
- Other
- Back to 5 day work weeks first week in November
- Guardrails done
- DMI no time to pave, Evans will try to get up here the following week to complete disaster work
Plan for the next two weeks
- Spot grading and leaf blowing roads for winter
- Loader service
- Swap cutting edge on loader bucket
- Finish Upper Podunk ditching for the season
- Cut brush on lower end of Fitts road
- Paving washout areas with Jason Evans
- T4 winter tires put on Thursday