Foreman’s Report 12-9-25
Work completed in the last two weeks
- Highway work completed
- Winter road maintenance, plowing, sanding
- Cleaned out shop bays
- Spillway project on Potter rd completed
- Prep trucks for next storm
- Salt/Sand
- Load of salt ordered 12-4
- Maintenance
- T2 first service done @ ATG
- T1 and T3 greased and inspected
- Loader cleaned and greased, plugged in during cold temps
- Chipper new wheels and tires swapped over
- Other
- Driveway permit for Quinn’s existing driveway
- Mirrors are on order for T2 for mounting on the hood
Plan for the next two weeks
- Replace work lights on loader and grader
- Fix drivers light on T1
- T2 to Westminster to get mirrors mounted
- Grader to nortrax for injector work
- Clean up old culverts at the dump