Foreman’s Report 2/25/2025
Work completed in the last two weeks
- Highway work completed
- Repaired culvert on S. Wardsboro rd, will need to repair blacktop in the spring
- Continuous road work (plowing, salting, sanding)
- Pushbacks are done and loader is making turnouts for water runoff
- Monitoring roads for mud as warm weather moves in
- Salt/Sand
- Ordered sand through Mitch as Derrig wasn’t keeping up last week
- Continually ordering salt as needed to keep shed full
- Maintenance
- Replaced broken air can on T1
- Changed oil in grader
- Grease equipment daily
- Dump
- Nothing to report
Plan for the next two weeks
- Clean up shop bays
- Clean and service trucks
- Monitor roads for mud
- Push back town for town meeting