Foreman’s Report 6/10/25
Work completed in the last two weeks
- Highway work completed
- Touch up road grading in areas that are needed
- Ditch work and road widening on Gilfeather Rd
- Underdrain installed on Gilfeather where water was boiling out of the road
- 3 culverts swapped out on Gilfeather to improve drainage and replace old worn out/collapsed pipe
- Road checks and tree removal during the heavy rain storms
- Salt/Sand
- Sand is getting delivered few loads a week
- Maintenance
- All dump truck tires swapped over in house
- Front end t1 and t3 checked over, brakes adjusted and greased, hub oil filled
- Grader blade swapped over
- Dump
- Brought down a load of tires to WSW
Plan for the next two weeks
- Road grading in areas that have scouring or washboards
- Continue on the road widening on Gilfeather road
- Place culvert order
- Review segments for grants in aid work for this year