Foreman’s Report 6-24-25
Work completed in the last two weeks
- Highway work completed
- Continued work on Gilfeather road improvements
- Replaced culverts on Main Street in prep for paving
- Started work on Bills rd to prep for paving
- Road checks and clearing trees/debris after wind storms
- Trimmed low hanging brush as were doing culvert work
- Salt/Sand
- Sand has started being delivered
- Maintenance
- Normal equipment/truck checks & greasing
- Dump
- Load of tires and light bulbs brought to bratt transfer station
- Cleaned up around dumpsters with Todd
- Other
- Culvert order has been delivered, billed for next fiscal year
- Worked on ROW for green mountain power
- Next 2 meetings available for road inspections with selectboard before selectboard meeting
- Picked up hay from Chapins
- Met with viking cives to go over new T2
Plan for the next two weeks
- Finish culverts on Bills rd
- Install new culvert on blackpiece
- Continue work on Gilfeather rd
- Touch up grading before the 4th of July