Foreman’s Report 8/12/25
Work completed in the last two weeks
- Highway work completed
- Culvert and ditch work in Sheldon Hill
- Touch up grading
- Roadside mowing is about halfway done
- Mulching roadsides on Gilfeather with excavator
- Trucked material to stock pile
- Salt/Sand
- Maintenance
- T1 was serviced at ATG
- Dump
- Freon was evacuated from a group of fridges and Todd is taking them apart and putting them in dumpsters
- Other
- Blackpiece rd, 3rd house has been building in the right of way
- GMP wants to bury power in Sheldon Hill, will gather more info
- Consolidated wants to bury communication on Sawmill Rd, permit and map will be available at meeting to discuss
Plan for the next two weeks
- Fall grading and spraying chloride
- More ditch work in Sheldon hill
- Top coating roads in Sheldon hill with cerpak
- Scour touchups from previous rain storms
- Continued tree work on East Hill