Foreman’s Report 8-26-25
Work completed in the last two weeks
- Highway work completed
- Graveled parts of Newell rd to gain cover over base material sticking out of road, graded out the road and applied chloride
- Roadside Mulching on Oak Hill for plans of ditching in the later part of September
- Roadside mulching Newell rd
- Trucked cerpak to stockpile
- Grading and putting down chloride on roads
- Salt/Sand
- Sand slowly getting delivered
- Maintenance
- Townline will be coming to service the loader and replacing serpentine belt and brake pads as well as general maintenance
- Dump
- Other
- Dropped off T2 at dealer and picked up our new tandem.
- Roadside mowing just has South Wardsboro to complete
Plan for the next two weeks
- Continue grading and getting chloride put down
- Continue mulching on Newell until road is completed, then move into ditch work and clean up a few culvert inlets
- Start on Grants in Aid work