Green Mountain Power work schedule 7/6 – 7/17
| Week of 6/29 | Week of 7/6 | Week of 7/13 |
| Upper and Lower Podunk Road/Smead Road/Potter Road Electrical: Monday – Thursday **Culvert Replacement/Backfill: Monday – Thursday Newfane Road Trenching: Monday – Thursday Electrical: Monday – Thursday **Culvert Replacement/Backfill: Monday – Thursday | Upper and Lower Podunk Road/Smead Road/Potter Road Electrical: Monday – Friday Newfane Road Trenching: Monday – Friday Electrical: Monday – Friday **Culvert Replacement/Backfill: Monday – Friday | Upper and Lower Podunk Road/Smead Road/Potter Road Electrical: Monday – Friday Newfane Road Electrical: Monday – Friday |
**CULVERT REPLACEMENT CAN CAUSE POTENTIAL ROAD CLOSURES; MEASURES WILL BE IN PLACE TO ALLOW TRAFFIC AS REQUIRED.